US 59 to IH 10
Segments H & I1

The Segment H & I-1 Draft Environmental Impact Statement (DEIS) was signed by the Federal Highway Administration on May 10, 2011 and was published in the State and Federal Registers on June 15, 2011 and June 24, 2011 respectively. The comment period will end September 21, 2011.

Second series of Public Scoping Meetings held May 8-9, 2007.
Public Scoping Meetings were held on Tuesday, February 28 and Wednesday, March 1 of 2006.
An agency meeting was held on Feb. 22, 2006 to brief state and federal resources agencies, local officials, and others about the proposed project and to solicit their comments.
In January 2006, a consultant team was given notice to proceed with preparing an Environmental Impact Statement (EIS) for Segments H and I-1.
 
Please click the icon below to access the corresponding agency’s website